Did anyone aware that PSSB the new developer who took over this project has no construction work in progress for nearly 2 months!?
Personnally I have went to PSSB subcontractor Ehsan Bina for an answer and have received advise that the reason work has stop is due to the public complains received by Ministry of Environment that the site has created pollution to the area and was given order by the Ministry of Environment to clear all wastes and dirts before re-start the construction.
In other hand, I have heard from a friend of mine that PSSB has not made any progress payment to its subcontractor and as at to-date amount owing is RM10.0million, hence the subcontractor has stop the work.
Would be much appreciated if someone could update us the latest status and site progress for NewGate 21.
Thank you.
Dear Dato',
It is very commendable of you to provide another avenue for the Newgate 21 buyers to share a common protal by introducing a new title "Newgate 21 Status" and for this I express my utmost gratitude. The current issue which was highlighted by Abby is indeed disturbing. I personally have called Yoga of PWC recently to ask on the matter and he mentioned that there was some issues between Pinggiran Setia and the subcontractors. Alas! the same issue again - non-payment by Pinggiran Setia to the subcontractors. Isn't this the same issue Solar Glow (previous developer) had? Is this a case of "pisang berbuah dua kali?". Haven't we learn any lessons from the past? How on earth did PWC identify Pinggiran Setia to be the developer then? I was made to understand that PWC's role is to manage the funds for this project. What happened to these funds? I would like to hear from PWC. I am not asking Dato' to do anything I understand that it is no more under your jurisdiction. We buyers are just leveraging on this portal. Maybe Pritpal and the committee could do their own investigations and report to the buyers what's happened. We'd rather hear from credible sources than making unfounded speculations. This is the least we deserve. On the speculation that work stopped due to orders from Ministry of Environment I certainly doubt this is true if any of the news reports on non-actions by the Ministry on much more serious environmental crimes are to go by. This is a simple case of dispute between Pinggiran Setia and the subcontractors which had victimised the buyers. We appreciate any party who can enlighten us further.